Three departments-milling (M), drilling (D), and sawing (S are assigned to three
ID: 2563703 • Letter: T
Question
Three departments-milling (M), drilling (D), and sawing (S are assigned to three work areas in Victor Berardis's Pieces moved per day between work areas are machine shop in Vent, Ohio. The number of work pieces moved per day and the distances between the centers of the work areas, in feet, are shown to the right. 32 18 It costs $2 to move 1 workpiece 1 foot The total material handling cost of the layout-s(enter your rosponao as a whole numberd Distances in feet between centers of the work areas are: 11 6Explanation / Answer
ans) the total material handling cost of the layout = 618
Flow X Distance x cost
M D S
M 264 (24 X 11 X 1) 192 (32 X 6 X 1)
D 162 (18 X 9 X 1)
S
___________________________________________________________
264 354
= 264 + 354 = 618
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.