Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

2017 2018 2019 2017 Cost to Date (12/31/17) 2018 Percent complete 2019 Less On M

ID: 2563281 • Letter: 2

Question

2017

2018

2019

2017

Cost to Date (12/31/17)

2018

Percent complete

2019

Less

On March 1, 2017, Sheffield Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,330,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below:

2017

2018

2019

Contract costs incurred during the year $2,671,200 $2,193,000 $2,395,800 Estimated costs to complete the contract at 12/31 3,688,800 2,395,800 –0– Billings to Fabrik during the year 3,170,000 3,510,000 1,650,000
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank.)

2017

Cost to Date (12/31/17)

$

2671200

Estimated Cost to Complete

3688800

   Total Cost

$

633600

Percent to complete

42

%

Revenue Recognized

$

2698600 (incorrect)

Costs Incurred

2671200

Profit/ Loss Recognized in 2017

$

27400 (inorrect)

2018

Costs to date (12/31/18)

$

4864200

Estimated Costs to Complete

2385800 (incorrect)

   Estimated Total Costs

$

7250000

(incorrect)

Percent complete

67

%

Revenue Recognized in 2018

$

2082500

Costs Incurred in 2018

2193000

   Profit / (Loss) Recognized in 2018   

$

(110500)

2019

total Costs Incurred

$

(INCORRECT)

Profit Previously RecognizedTotal Costs IncurredProfit / (Loss) Recognized in 2019Total Revenue RecognizedTotal Profit on ContractEAT_1364799800488_0_2561446869231341 (INOCRRECT)

(INCORRECT)

Total Profit on ContractProfit / (Loss) Recognized in 2019Profit Previously RecognizedTotal Costs IncurredTotal Revenue RecognizedEAT_1364799800488_0_5460163114080155    (INCORRECT

2748900 (INCORRECT)

Less

:

Profit / (Loss) Recognized in 2019Total Revenue RecognizedTotal Costs IncurredTotal Profit on ContractProfit Previously RecognizedEAT_1364799800488_0_2561446869231341 (INCORRECT)

(INCORRECT

Profit. (Loss) Recognized in 2019

$

353100


(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any fields blank. Enter loss using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)
2017 $

0

2018 $

0

2019 $

1070000

Explanation / Answer

(a) 2017

Cost incurred upto date = $2671200

Estimated cost to complete the contract = $3688800

Total cost = $6360000

Percentage of completion = 2671200÷6360000 =42%

Revenue to be recognised = total contract value × 42%

= 8330000×42% = $3498600

- cost incurred upto date =$2671200

= profit to be recognised = $827400

2018

Cost incurred upto date = 2671200+2193000 = $4864200

Estimated cost of completion = 2395800

Total cost = $7260000

Percentage of completion = 4864200÷7260000 = 67%

Revenue to be recognised = $8330000×67% = $5581100

- cost incurred upto date = $4864200

= profit to be recognised = $716900

(-) profit recognised in earlier year = $827400

= profit to be recognised in 2018 = ($110500)

2019

cost incincurred upto date= $7260000

Contract revenue =$8330000

Percentage of completion = 100%

Revenue to be recognised =8330000

-) cost = $7260000

= profit on contract = $1070000

(-) profit recognised in earlier years = $716900

= profit to be recognised in 2019 = $353100

(b) Revenue under completed contract method will be recognised only in the year in which contract gets completed.

So in 2019 revenue will be recognised as under

Total revenue = $8330000

(-) total cost = $7260000

= profit = $1070000

And in 2017 and 2018, no profit will be recognised as the contract is not completed.