During May, Joliet Fabrics Corporation manufactured 540 units of a special multi
ID: 2558778 • Letter: D
Question
During May, Joliet Fabrics Corporation manufactured 540 units of a special multilayer fabric with the trade name Stylex. The following information from the Stylex production department also pertains to May. Direct material1 purchased: 18,400 yards at $1.42 per yard $26,128 Direct material used: 9,900 yards at ?1.42 per yard Direct labor 2,500 hours at $9.19 per hour 14,058 22,975 The standard prime costs for one unit of Stylex are as follows: Direct material: 20 yards at $1.39 per yard$27.80 Direct labor: 4 hours at $8.00 per hour 32.00 Total standard prime cost per unit of output $59.80 Required: Compute the following variances for the month of May. (Indicate the effect of each variance by selecting "Favorable" or "Unfavorable". Select "None" and enter "O" for no effect (i.e., zero variance) 1. Direct-material price variance 2. Direct-material quantity variance Direct-material purchase price variance 4. Direct-labor rate variance 5. Direct-labor efficiency varianceExplanation / Answer
Part 1 -- Material Price Variance
Material Price Variance is the variance arises in the material cost due to difference in actual material purchase price from standard material price. Mathematically, it is calculated as below:
Material Price Variance = Actual Quantity (Standard Price – Actual Price)
Note --- Here actual quantity means actual quantity of material PURCHASED. If the question does not provide the information about material purchase, it is taken as equal to material consumed.
Direct Material Price Variance
Actual Price (AP) (282,000 / 12,000)
$1.420
per yard
Standard Price (SP)
$1.390
per yard
Variance or Difference in Price
$0.030
per yard
x Actual Quantity PURCHASED
18400
ounce
Material Price Variance
$552
Unfavorable
Unfavorable because actual cost paid for material purchase is higher than anticipated.
Part 2 --- Material Quantity/Efficiency/Usage Variance
Material Efficiency (Usage) Variance measures variance in material cost due to usage/consumption of materials. It is calculated as below:
Material Quantity Variance = Standard Price (Standard Quantity for Actual Production – Actual Quantity USED)
Note --- Here actual quantity means actual quantity of material CONSUMED/USED
Direct Material Quantity Variance
Standard Quantity Allowed for actual production:
Actual Production/Activity
540
Units
x Allowed Standard Quantity Per Unit
20
Yards
Total Standard Quantity Allowed for actual production (SQAP)
10800
Yards
Actual Quantity USED (AQU)
9900
Yards
Variance or Difference in Quantity (AQU - SQAP)
900
ounce
x Standard Price (SP)
$1.39
per yard
Material Quantity Variance
$1,251
Favorable
Favorable because actual quantity used is less than standard quantity at standard cost
Part 3 – Direct material purchase price variance = Material Price Variance $552 U + Material Quantity Variance $1251 F
= $699 Favorable
Part 4 – Labor Rate Variance
Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:
Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)
Here, actual time means time for which wage has been paid.
Labor Rate Variance
Actual Hourly Rate (AHR)
$9.19
Per Hour
Standard Hourly Rate (SHR)
$8.00
Per Hour
Variance or Difference in Rate
$1.19
Per Hour
x Actual Labor Hours worked
2500
Hours
Labor Rate Variance
$2,975
Unfavorable
Unfavorable Labor Rate Variance because actual hourly rate paid is higher than standard hourly rate.
Part 5 -- Labor Quantity Variance
Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.
Labor Quantity / Efficiency Variance
Standard Hours Allowed for actual production:
Actual Production
540
Units
x Allowed Standard Hours Per Unit
4
hours
Total Standard Hours Allowed for actual production (SHAP)
2160
hours
Actual Labor Hours Worked (AH)
2500
hours
Variance or Difference in Hours (AH - SHAP)
340
hours
x Standard Hourly Rate (SHR)
$8.00
per hour
Labor Efficiency Variance
$2,720
Unfavorable
Unfavorable Labor Efficiency Variance because the Actual Hours Worked is higher than the allowed standard hours at standard rate
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Direct Material Price Variance
Actual Price (AP) (282,000 / 12,000)
$1.420
per yard
Standard Price (SP)
$1.390
per yard
Variance or Difference in Price
$0.030
per yard
x Actual Quantity PURCHASED
18400
ounce
Material Price Variance
$552
Unfavorable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.