Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial pro

ID: 2556839 • Letter: J

Question

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $280,000, and budgeted direct labor hours were 16,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow: Job 39 Job 40 Job 41 Job 42 Beginning balance $22,400 $35,100 $17,100 $1,900 Materials requisitioned 19,200 21,800 12,700 12,100 Direct labor cost 10,300 18,900 7,350 3,000 Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 110 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Required:

1. Calculate the overhead rate based on direct labor cost.

% of direct labor cost

2. Set up a simple job-order cost sheet for all jobs in process during June.

Naranjo Company Job-Order Cost Sheets

Job 39 Job 40 Job 41 Job 42

Balance, June 1 $ $    $ $

Direct materials    $    $ $ $

Direct Labor $    $    $ $

Total $    $ $    $

3. What if the expected direct labor rate at the beginning of the year was $28 instead of $35? What would the overhead rate be? If required, round your overhead rate answer to one decimal place.

New budgeted direct labor cost = $

New overhead rate = % of direct labor cost

Explanation / Answer

Req 1. Estimated Overheads: $ 280,000 Direct Labour hours: 16000 DLH Labour rate per hour: $ 35 per hour Labour cost (16000hrs@35): $560,000 Pre-determined OH rate: Estimated Overheads / Direct labour cost *100 280,000 /560,000 *100 = 50% of labour cost Req 2: Job 39 Job 40 Job 41 JOB 42 Beginning Cost 22400 35100 17100 1900 Material 19200 21800 12700 12100 Labour 10300 18900 7350 3000 Overheads 5150 9450 3675 1500 (50% of labour cost) Total Cost 57050 85250 40825 18500 Status Sold Finished Goods WIP WIP Req 3 Estimated Overheads: $ 280,000 Direct Labour hours: 16000 DLH Labour rate per hour: $ 28 per hour Labour cost (16000hrs@28): $448,000 Pre-determined OH rate: Estimated Overheads / Direct labour cost *100 $ 280,000 /448,000 *100 = 62.50% New Budgeted labour cost 448,000 New OH rate: 62.50% on direct labour cost

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote