Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Help The following data are the actual results for Marvelous Marshmallow Company

ID: 2556341 • Letter: H

Question

Help The following data are the actual results for Marvelous Marshmallow Company for October Actual out put Actual variable overhead $409,000 Actual fixed overhead Actual machine time 12,000 cases $172,000 40,500 machine hours Standard cost and budget information for Marvelous Marshmallow Company follows: Standard variable-overhead rate Standard quantity of machine hours Budgeted fixed overhead Budgeted output 10.00 per machine hour 3 hours per case of marshmallows $168,000 per month 14,000 cases per month Required: Use any of the methods explained in the chapter to compute the following variances. (Indicate the effect of each variance b selecting "Favorable" or "Unfavorable". Select "None" and enter "o" for no effect (i.e., zero variance).) a. Variable-overhead spending variance b. Variable-overhead efficiency variance c. Fixed-overhead budget variance d. Fixed-overhead volume variance Unfavorable Unfavorable Unfavorable Unfavorable

Explanation / Answer

Calculation of variances :

Variable overhead spending variance:

( also known as variable overhead rate variance and variable overhead expenditure variance )

We can calculate the variable overhead spending variance by using fallowing formula.

=Actual Hour (Standard variable overhead rate per unit-Actual variable overhead Rate per unit)

Hence

Actual hour =40500

Standard Variable overhead rate= $10 per Machine hour

Actual Variable overhead rate     =Actual Variable Overhead/ Actual machine hour ( $409000/40500) = $10.098

Applying the formula

40500($10-10.098)= 3969 unfavourable

2) Variable overhead efficiency variance:

Standard rate (Standard Machine Hour-Actual Machine Hour)

Standard machine hour = (Stand. Hour P.U* Standard Output) > 3*14000 = 42000 Hours

$10(42000-40500)= $15000 favourable

3) Fixed Overhead Budget Variance

= Total Budgeted Fixed Overhead-Actual Fixed Overhead

=$168000-$172000= $4000 unfavourable

4) Fixed Overhead Volume Variance

= Standard Fixed Cost – Budgeted Fixed Cost

Standard Fixed Cost =Total Budgeted Fixed Cost/ Total Budgeted Unit*Actual Unit

$168000/14000*12000

Apply the formula

$144000-$168000= $24000 unfavourable

Hence

Variable overhead spending variance       $3969 unfavourable   

Variable overhead efficiency variance      $15000 favourable

Fixed Overhead Budget Variance               $4000 unfavourable

Fixed Overhead Volume Variance              $24000 unfavourable

Part II

1) Variable Overhead Spending variance:

=Actual Hour (Standard variable overhead rate per unit-Actual variable overhead Rate per unit)

291000 Hour ( $12-18.763) =$1968033 Unfavourable

Actual variable overhead rate= (Actual Overhead/Actual labour hour)> 5460000/291000= 18.763

2) Variable overhead efficiency variance

= Standard rate (Standard Hour-Actual Hour)

$12(308000-291000) =$204000 Favourable

3)Fixed Overhead Budgeted variance

    = Total Budgeted Fixed Overhead-Actual Fixed Overhead

Total Budgeted Fixed Overhead= Total Hours* Fixed OH Rate per hour

=308000*22= $6776000

Applying formula

$6776000-$8025000= $1249000 Unfavourable

4)Fixed Overhead volume variance

      = Standard Fixed Cost – Budgeted Fixed Cost

Std. Fixed Cost= (Total Budgeted Fixed Cost/ Total Budgeted Unit*Actual Unit) > ($6776000/61600)*58600=$6446000

Applying Formula

$6446000-$6776000= $330000 Unfavourable

Hence:

Variable overhead spending variance       =$1968033 Unfavourable   

Variable overhead efficiency variance      =$204000 Favourable

Fixed Overhead Budget Variance               =$1249000 Unfavourable

Fixed Overhead Volume Variance              =$330000 Unfavourable

Part iii

Calculation of total standard hour:

1) Field model require 7 Direct labour hour

Total Production 300 field model

Total labour hour required= 300*7= 2100 hours

2) Professional model required 9 hour

Total unit of professional model is manufacturer 400

Total labour hour required= 400*9 =3600 hour

Hence total standard hour allowed 2100 Hrs+3600 hrs= 5700 Hrs