[VARIANCE ANALYSIS] The following is total monthly budgeted cost and activity in

ID: 2555581 • Letter: #

Question

[VARIANCE ANALYSIS]

The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company:

Variable

Fixed

Cost Driver

$80,982

$157,000

3,300 labor hours

$9,504

$21,000

2,700 letters

$120,000

$88,000

2,400,000 lines

$11,180

$77,000

21,500 accounts


In September, actual costs and activity were as follows:

Total Costs

Driver Amount

$242,736

3,480 labor hours

$30,010

2,500 letters

$198,969

2,220,000 lines

$87,502

21,620 accounts


Required
Compute the flexible-budget variances for the following two activity cost items (round all answers to the nearest dollar and enter favorable variances as positive numbers and unfavorable variances as negative numbers):

  Correspondence    

  Account inquiry   

Activity Center

Variable

Fixed

Cost Driver

Account inquiry

$80,982

$157,000

3,300 labor hours

Correspondence

$9,504

$21,000

2,700 letters

Account billing

$120,000

$88,000

2,400,000 lines

Bill verification

$11,180

$77,000

21,500 accounts

Explanation / Answer

Compute the flexible-budget variances for the following two activity cost items

Flexible budget Actual Variance Correspondence    29800 30010 -210 U Account inquiry 199000 198969 31 F