Window Help Save & Exit Sube Indiana Co. began During 2018, Indiana incurred $37
ID: 2555440 • Letter: W
Question
Window Help Save & Exit Sube Indiana Co. began During 2018, Indiana incurred $37 million of costs a construction project in 2018 with a contract price of $164 million to be received when the project is completed in 2020 and estimates an additional $83 million of costs to complete the project Indiana recognizes over time and for this project recognizes revenue over time according to the percentage of the project that has been completed Multiple Choice Recognized $8100 million loss on the project in 2018 Recognized no gross profit or loss on the project in 2018 MacBook Air 5 6 7 8 9Explanation / Answer
total cost of the project =$ 164 miilion
cost Incurred =$ 37 Million
Cost to be Incurred = $ 83 million
Profit to be recognised= 164-37-83=$44 million
Profit earned in 2018 = 44 X 37 / (83+37)= $13.57 million G.P in the year 2018
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.