Seasons Construction is constructing an office building under contract for Canno
ID: 2553060 • Letter: S
Question
Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. 18). Seasons Construction completes the remaining 25% of the building construction on December 31, 2020, as scheduled. At that time the total costs of construction are $18,750,000.
What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2020?
Revenue Expenses
a. $18,600,000 $18,750,000
b. $4,650,000 $ 4,687,500
c. $4,650,000 $ 5,250,000
d. $4,687,500 $ 4,687,500
the answer is C but I am not getting how the expense is being calculated. Please explain.
Explanation / Answer
total contract price is $ 18,600,000
season construction using percentage of completion method.
Amount of revenue & construction expense for the year ended december 31, 2020 will be
25% of $ 18,600,000 revenue = $ 4,650,000
25% of $ 18,750,000 total cost = $ 4,687,500
Hence , answer is c.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.