Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following information pertains to the standard costs and actual activity for

ID: 2551405 • Letter: T

Question

The following information pertains to the standard costs and actual activity for Tyler Company for September:

Direct materials 4 units of material A × $2.00 per unit

1 unit of material B × $3.00 per unit

Direct labor 3 hours × $8.00 per hour

Activity for September

Materials purchased

Material A 3,400 units × $2.05 per unit

Material B 800 units × $3.10 per unit

Materials used

Material A 3,050 units

Material B 705 units

Direct labor used 2,050 hours × $8.30 per hour

Production output 700 units

There were no beginning direct materials inventories.

(a) Determine the materials price and quantity variances.

(b) Determine the labor rate and efficiency variances.

Explanation / Answer

a) Material price and quantity variance :

Material price A Variance = (2-2.05)*3400 = 170 U

Material quantity variance = (700*4-3050)*2 = 500 U

Material price B Variance = (3-3.10)*800 = 80 U

Material quantity variance = (700*1-705)*3 = 15 U

2) Direct labour rate variance = (8-8.30)*2050 = 615 U

Direct labour efficiency variance = (700*3-2050)*8 = 400 F