The following information pertains to the standard costs and actual activity for
ID: 2551405 • Letter: T
Question
The following information pertains to the standard costs and actual activity for Tyler Company for September:
Direct materials 4 units of material A × $2.00 per unit
1 unit of material B × $3.00 per unit
Direct labor 3 hours × $8.00 per hour
Activity for September
Materials purchased
Material A 3,400 units × $2.05 per unit
Material B 800 units × $3.10 per unit
Materials used
Material A 3,050 units
Material B 705 units
Direct labor used 2,050 hours × $8.30 per hour
Production output 700 units
There were no beginning direct materials inventories.
(a) Determine the materials price and quantity variances.
(b) Determine the labor rate and efficiency variances.
Explanation / Answer
a) Material price and quantity variance :
Material price A Variance = (2-2.05)*3400 = 170 U
Material quantity variance = (700*4-3050)*2 = 500 U
Material price B Variance = (3-3.10)*800 = 80 U
Material quantity variance = (700*1-705)*3 = 15 U
2) Direct labour rate variance = (8-8.30)*2050 = 615 U
Direct labour efficiency variance = (700*3-2050)*8 = 400 F
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.