PLEASE SHOW SOLUTION. DROP DOWN OPTIONS ARE FAVORABLE OR UNFAVORABLE.
Exercise 6-1 Crane Paints manufactures artist's oil paints. Each 40 ml tube of paint requires 5 minutes of direct labor, and the standard labor rate is $7.86 per direct labor hour. In September, Crane incurred 1360 direct labor hours at a cost of $86,000 to produce 124,100 tubes of paint. Calculate Crane's direct labor rate variance for September. (Round answer to o decimal places, e.g. 125. If variance is zero, select "Not Applicable" and enter 0 for the amounts.) Direct labor rate variance 5 Click if you would like to Show Work for this question:Explanation / Answer
Direct labour rate variance = (Standard rate-actual rate)actual hour
= (7.86*11360-86000)
Direct labour rate variance = 3290 Favorable
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.