Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

- You are dealing with units, not dollars. - Note that the BWIP came from Januar

ID: 2548290 • Letter: #

Question

- You are dealing with units, not dollars.

- Note that the BWIP came from January 20% completed with respect to conversion costs, which means that we need 80% more conversion in February to finish them.

- Note that under FIFO, only current costs should be considered in the computation

- We need the following costs:

1-      Cost of BWIP

2-      Cost of Units Started and Completed

3-      Cost of the EWIP

- Follow the format below:

Costs to be accounted for:

-          Prior Cost (coming from January): ……………………….

-          Current Cost (incurred in February): …………………….

Total cost to be accounted for:               …………………………

Costs accounted for:

-          Cost of BWIP:                                            …………………

-          Cost of Units Started and Completed:      …………………

-          Cost of the EWIP:                                      …………………

Total cost accounted for:                                ………………..

Swasey Fabrication, Inc. of Tulsa, Oklahoma, manufactures frames for motorcycles. Each frame passes through three process departments: (1) Cutting, (2) Welding, and (3) Painting. In February 2018, the Cutting Department reported the following data: a) In cutting, all direct materials are added at the beginning of the production procesS b) Beginning Work in Process consisted of 40,000 units, 20% complete with respect to conversion costs. Costs in the Beginning Work in Process included direct materials for S500,000; direct labor for $300,000; and applied factory overhead for $156,000. c) Costs added to production during the month of February 2018 were direct materials for $2,565,000; direct labor for $3,471,150; overhead was assigned to production based on activity-based costing using the following information: Activit Inspection Maintenance Receiviin Activity Rate S150 per inspection hour5,000 inspection hours $750 per maintenance hour3,000 maintenance hours $300 per receiving order Activity Driver Usage 2,000 receiving orders d) At the end of the month, 122,000 units were finished and transferred out to the Welding Department, leaving 14,000 units in the ending Work in Process, completed up to 25%) Required: Prepare Swasey February production report using the FIFO method (please, show clearly all calculations; round unit costs to closest two decimals)

Explanation / Answer

Given information -

Flow of physical units of output -

Computation of Equivalent unit for Direct material conversion cost, and factory overheads -

Calcualtion of Equivalent cost per unit and assign cost to the units completed (and transferred out) and units in Ending WIP -

As per format given in question :

Note - all values are in $.

Please comment in case of any clarification required/wrong answer.

Particulars Physical units % complete material conversion factory overheads WIP, Beginning 40000 20% 20% 20% started into production 96000 completed & transferred out 122000 WIP, Ending 14000 100% 25% 25%