Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs pro
ID: 2548014 • Letter: P
Question
Predetermined Overhead Rate, Applied Overhead, Unit Cost
Ripley, Inc., costs products using a normal costing system. The following data are available for last year:
Overhead is applied on the basis of direct labor hours.
Required:
1. What was the predetermined overhead rate?
$ per direct labor hour
2. What was the applied overhead for last year?
$
3. Was overhead over- or underapplied, and by how much?
Underapplied overhead = $
4. What was the total cost per unit produced? (Carry your answer to four significant digits.)
$ per unit
Explanation / Answer
1. What was the predetermined overhead rate?
Predetermine overhead rate = 263200/9400 = 28 per labour hour
2. Applied overhead = 9100*28 = 254800
3. Under applied overhead = 254800-262400 = 7600
4) Total cost per unit = (1185200+254800/160000) = 9 per unit