Question 3 Job 819 was started in October. During the month, direct materials fo
ID: 2547778 • Letter: Q
Question
Question 3
Job 819 was started in October. During the month, direct materials for the job cost $4,000. Direct labor hours of 200 were worked. (The direct labor pay rate is $20 per hour.) Manufacturing overhead is applied at $15 per direct labor hour. What was the total cost of Job 819 in October?
Flag this Question
Question 4
Nguyen Engineering uses project costing to assess the profitabilty of their projects. They should notinclude which of the following costs in their estimate of overhead?
$7,000Explanation / Answer
Question 3
Total cost = Direct materials + Direct labour + Manufacturing overhead
Total cost = $4,000 + (200hours*$20/hour) + (200hours*$15/hour)
Total cost = $4,000+ $4,000 + $3,000
Total cost = $11,000