Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptica

ID: 2545288 • Letter: P

Question

Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Fabrication Assembly Setup Inspecting Production scheduling Purchasing The activity-base usage quantities and units produced for each product were as follows Activity Base Machine hours DIrect labor hours Setups Inspections Production orders Purchase orders Units produced Activity Rate $30 per machine hour $13 per direct labor hour $52 per setup $22 per Inspection $14 per production order $11 per purchase order Elliptical Machines Treadmill 1,878 453 61 660 71 195 240 1,108 19 396 119 161

Explanation / Answer

Answer

Elliptical Machines

TreadMills

Activities

Activity rates $ -(A)

No. of activities (B)

Cost allocated (A x B)

No. of activities (C )

Cost allocated (A x C)

Fabrication

30

1878

56340

1108

33240

Assembly

13

453

5889

177

2301

Setup

52

61

3172

19

988

Inspecting

22

660

14520

396

8712

Production scheduling

14

71

994

14

196

Purchasing

11

195

2145

119

1309

Total cost allocated

$83060

Total cost allocated

$46746

Total Units

240

Total Units

161

Activity cost per unit

$346.083

Activity cost per unit

$290.3478

Total Activity Cost

Activity Cost per unit

Elliptical Machines

$83060

$346.08

Tread Mills

$46746

$290.35

Elliptical Machines

TreadMills

Activities

Activity rates $ -(A)

No. of activities (B)

Cost allocated (A x B)

No. of activities (C )

Cost allocated (A x C)

Fabrication

30

1878

56340

1108

33240

Assembly

13

453

5889

177

2301

Setup

52

61

3172

19

988

Inspecting

22

660

14520

396

8712

Production scheduling

14

71

994

14

196

Purchasing

11

195

2145

119

1309

Total cost allocated

$83060

Total cost allocated

$46746

Total Units

240

Total Units

161

Activity cost per unit

$346.083

Activity cost per unit

$290.3478