Antuan Company set the following standard costs for one unit of its product. Dir
ID: 2543190 • Letter: A
Question
Antuan Company set the following standard costs for one unit of its product. Direct materials (4.8 Ibs.$5.00 per Ib.) Direct labor (1.7 hrs. $13.00 per hr.) Overhead (1.7 hrs. $18.50 per hr.) Total standard cost $20.00 22.10 31.45 $73.55 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory's capacity of 20,000 units per month. Following are the company's budgeted overhead costs per month at the 75% capacity level. Overhead Budget (75% Capacity) Variable overhead costs Indirect materials Indirect labor Power Repairs and maintenance Total variable overhead costs $ 15,000 75,000 15,000 30,000 $135,000 Fixed overhead costs Depreciation-Building Depreciation-Machinery Taxes and insurance Supervision Total fixed overhead costs 25,000 72,000 16,000 223,750 336,750 $471,750 Total overhead costs The company incurred the following actual costs when it operated at 75% of capacity in October Direct materials (60,500 Ibs. $5.20 per lb. Direct labor (28,000 hrs. $13.30 per hr.) Overhead costs $ 314,600 372,400 Indirect materials Indirect labor Power Repairs and maintenance Depreciation-Building Depreciation-Machinery Taxes and insurance Supervision $ 41,300 176,450 17,250 34,500 25,000 97,200 14,400 223,750 629,850 $1,316,850 Total costsExplanation / Answer
Antuan Company Overhead Variance Report Expected production volume 75% of capacity production level achieved 75% of capacity Volume variance No variance Flexible Actual Variances Fav/unfav budget results Variable Costs Indirect materials 15,000 41,300 26,300 U Indirect labor 75,000 176,450 101,450 U Power 15,000 17,250 2,250 U Repairs & Maintenance 30,000 34,500 4,500 U total variable costs 135,000 269,500 134,500 U Fixed costs Depreciation-Building 25,000 25,000 0 N Depreciation-Machinery 72,000 97,200 25,200 U Taxes and insurance 16,000 14,400 1,600 F Supervision 223,750 223,750 0 N total fixed costs 336,750 360,350 23,600 U total overhead costs 471,750 629,850 158,100 U
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.