Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 11 Let\'s imagine that you graduated from RBS and have become a success

ID: 2540925 • Letter: Q

Question

Question 11 Let's imagine that you graduated from RBS and have become a successful management consultant. Planning your work for the next month, you have realized that you have committed yourself to four projects with deadline in four weeks' time. You work a maximum of 8 hours per day, five times a week, and you are determined to continue to preserve your life-work balance (no overtime). As you are the only expert in your field of knowledge, you cannot outsource your projects to anybody you know. Using the Theory of Constraints' methodology, prioritize your projects, using the following information. Please note that we assume that you can work only on one project at a time. (Hint: use working hours as a constraint.) Project Pojc Project Project Projects Estimated revenue upon 5.0003,000 10,0009,000 27,000 completion of a project Estimated costs for a project Number of hours you need to 1,000 ,500 4,000 3,000 9,500 complete each project 50 10 120 60 240

Explanation / Answer

Solution:

The problem is related to “Theory of Constraints” i.e. Resources in Scarcity.

Here Number of hours are limited to total 160 hours for a 4 weeks month.

Number of Hours Available = 8 hrs in a day x 5 days per week x 4 weeks per month

= 160 Hours

Key factor is the factor which is under scarcity. IN this case, we need to priorities the work based on the highest profit per limiting factor. So we need to calculate the Profit per project per hours.

Project

A

B

C

D

Estimated revenue upon completion of a project

$5,000

$3,000

$10,000

$9,000

Less: Estimated costs for a project

$1,000

$1,500

$4,000

$3,000

Estimated Profit from a Project (A)

$4,000

$1,500

$6,000

$6,000

Number of hours required to complete each project (B)

50

10

120

60

Estimated Profit of a project per hour (A/B)

$80

$150

$50

$100

Ranking / Priority of Project

3

1

4

2

Priorities

Rank 1 --- Project B is to be done first, since it has highest Estimated Profit per hour. 10 Hours

Rank 2 – Project D. 60 Hours

Rank 3 – Project A. 50 Hours

Rank 4 – Project C --- It will not be done since total available hours are 160 hours and this project requires 120 Hours.

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Project

A

B

C

D

Estimated revenue upon completion of a project

$5,000

$3,000

$10,000

$9,000

Less: Estimated costs for a project

$1,000

$1,500

$4,000

$3,000

Estimated Profit from a Project (A)

$4,000

$1,500

$6,000

$6,000

Number of hours required to complete each project (B)

50

10

120

60

Estimated Profit of a project per hour (A/B)

$80

$150

$50

$100

Ranking / Priority of Project

3

1

4

2

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote