Bramble Fabrication produces custom-made security doors and gates. Currently two jobs are in process, 359 and 360. During production of Job 359, the supervisor was on vacation, and the employees made several errors in cutting the metal pieces for the two doors in the order. The spoiled metal pieces cost $20 each and had zero scrap value. In addition, an order of five gates that had been manufactured for Job 360 required a fine wire mesh that sometimes tore as it was being mounted. Because a similar wire could be used that was much easier to install, the customer had been warned that costs could run over the bid if any difficulty was encountered in installing the wire. One of the gates was spoiled during the process of installing the wire. The cost of the materials and direct labour for the gate was $138. The gate and metal were hauled to the dump and discarded.
Prepare spoilage journal entries for both job 359 and job 360.
Explanation / Answer
1 Loss from abnormal spoilage 20 Work in progress cotrol (Job 359) 20 2 Work in progress control (job 360) 138 Various accounts 138
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.