What figures? Expected overhead cost and related data for the two production dep
ID: 2539043 • Letter: W
Question
What figures?
Expected overhead cost and related data for the two production departments follow.
Explanation / Answer
Solution:
Part 1 -- Plant wide overhead rate based on direct labor hours
Predetermined Plant Wide Overhead Rate
- Overheads are the indirect manufacturing costs incurred on the making of product. These costs are not directly traceable with the production volume because it incurred for a period or in lum sum amount.
- Generally, the overhead costs are apply to the production department on predetermined basis.
- Predetermined Overhead Rate is the rate which is used to apply manufacturing overhead to products or job orders.
- Normally, it is calculated at the beginning of the period.
- It is calculated by dividing the estimated factory overhead cost by an allocation base (or suitable basis).
- Allocation bases may be direct labor hours, direct labor costs, machine hours etc..
Predetermined Overhead Rate = Estimated Manufacturing Overhead Cost / Estimated Allocation Base
Plant-wide overhead rate means predetermined overhead rate of plant as a whole.
Estimated Total Manufacturing Overhead
($340,000 + $415,000)
$755,000
$1.66 per direct labor hour
($755,000 / 455,000)
Estimated Total Direct Labor Hours
(150,000 + 305,000)
455,000 DLHs
Plantwide Overhead Rate = $1.66 per direct labor hour (Rounded to 2decimal places)
Part 2 – Total Manufacturing Cost per unit
$$
Direct materials
$260,000
Direct Labor ($182,000 + $400,000)
$582,000
Applied Manufacturing Overhead
Fabricating Dept. (6500 DLH * $1.66)
$10,790
Assembly Dept. (16000 DLH * $1.66)
$26,560
Total Manufacturing Costs
$879,350
Units Produced
21000
Manufacturing Cost per unit
$41.87
Part 3 – Departmental Overhead Rate
Department
Fabricating
Assembly
Overhead Cost
$340,000
$415,000
Allocation Base
Machine Hours for Fabricating Dept.
156,000 MHs
Direct Labor Hours for Assembly
305,000 DLHs
Overhead Rate (Overhead Cost / Allocation Base)
$2.18
$1.36
Departmental Overhead Rate
Fabricating
$2.18
Per machine hour
Assembly
$1.36
Per direct labor hour
Part 4 – Manufacturing Cost per unit
$$
$$
Direct materials
$260,000
Direct Labor
Fabricating Dept.
$182,000
Assembly Dept.
$400,000
Total Direct Labor Cost
$582,000
Applied Manufacturing Overhead
Fabricating Dept. (14,400 MHs * $2.18)
$31,392
Assembly Dept. (16000 DLH * $1.36)
$21,760
Total Applied Overhead Cost
$53,152
Total Manufacturing Costs
$895,152
Units Produced
21000
Manufacturing Cost per unit
$42.63
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Estimated Total Manufacturing Overhead
($340,000 + $415,000)
$755,000
$1.66 per direct labor hour
($755,000 / 455,000)
Estimated Total Direct Labor Hours
(150,000 + 305,000)
455,000 DLHs
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.