A company provided the following direct materials cost information. Compute the
ID: 2538728 • Letter: A
Question
A company provided the following direct materials cost information. Compute the direct materials price variance. Standard costs assigned: Direct materials standard cost (421,000 units @ $3.30/unit) $ 1,389,300 Actual costs: Direct Materials costs incurred (418,200 units @ $3.40/unit) $ 1,421,880 Multiple Choice $41,820 Unfavorable. $41,820 Favorable. $42,100 Favorable. $1,389,300 Unfavorable. $1,389,300 Favorable.
MC Qu. 47 A company provided the following... A company provided the following direct materials cost information. Compute the direct materials price variance. Standard costs assigned: Direct materials standard cost (421,000 units @ $3.30/unit) Actual costs: Direct Materials costs incurred (418,200 units $3.40/unit) $1,421,880 $1,389,300 Multiple Choice $41,820 Unfavorable. $41,820 Favorable $42,100 Favorable. $1,389,300 Unfavorable. $1,389,300 FavorableExplanation / Answer
Calculation of direct material price variance:
Direct material price variance= ( Standard price- Actual price)*Actual quantity
=(3.30-3.40)*418200= -$41820
Direct material price variance is $41820 Unfavourable