The information below pertains to July production at Padro ?Company\'s paint? fa

ID: 2533258 • Letter: T

Question

The information below pertains to July production at Padro ?Company's paint? factory, which produces paints for household? interiors:

                                                            Gallons                 Materials                            Conversion

Work in process, July 1                  4,000                    40% complete                   10% complete

Started in July                                  3,600

To account for                                 7,600

Completed and transferred out 6,200                    100% complete                 100% complete

Work in process, July 31 1,400                                   30% complete                   20% complete

Accounted for                                  7,600

Requirement

Using the? weighted-average method, determine the number of equivalent units of production for materials and conversion during July

   Equivalent Units

                                                            Physical

Physical Flow                                   Units                     Materials             Conversion

Work in process, July 1                  4,000

Started in July                                  3,600

To account for                                 7,600

Completed and transferred out 6,200                    ________            _________

Work in process, July 31 1,400                                   ________            _________

Accounted for                                  7,600

Work done this period                                                 ________            ________

Explanation / Answer

Physical units Materials Conversion Work in process, July 1   4000 Started in July    3600 To account for   7600 Completed and transferred out 6200 6200 6200 Work in process, July 31 1400 420 280 Accounted for 7600 Work done this period 6620 6480