Required information [The following information applies to the questions display
ID: 2528763 • Letter: R
Question
Required information
[The following information applies to the questions displayed below.]
Sedona Company set the following standard costs for one unit of its product for 2017.
The $5.60 ($4.00 + $1.60) total overhead rate per direct labor hour is based on an expected operating level equal to 75% of the factory's capacity of 50,000 units per month. The following monthly flexible budget information is also available.
During the current month, the company operated at 70% of capacity, employees worked 340,000 hours, and the following actual overhead costs were incurred.
AH = Actual Hours
SH = Standard Hours
AVR = Actual Variable Rate
SVR = Standard Variable Rate
SFR = Standard Fixed Rate
Explanation / Answer
1 variable overhead spending variance=(Standard Rate-Actual Rate)*actual hours worked (4-1375000/340000)*340000 $ 15,000.00 unfavourable variable overhead efficiency variance=(Standard hour-Actual hour)*Standard rate (350000-340000)*4 $ 40,000.00 Favourable 2 fixed overhead spending variance=Actual fixed overhead-Budgeted fixed overhead (628600-600000) $ 28,600.00 Unfavourable fixed overhead volume variance=Absorbed fixed overhead-Budgeted fixed overhead (350000 hours*1.60 per hour-600000) $ 40,000.00 unfavourable 3 Controllable Variance=Actual overhead-(budgeted allowance based on standard hours allowed) (2003600-2000000) $ 3,600.00 unfavourable budgeted allowance based on standard hours allowed Fixed $ 600,000.00 variable-35000 units *10hours*4 per hour $ 1,400,000.00
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.