The records of Norton, Inc. show the following for July: Standard labor-hours al
ID: 2528226 • Letter: T
Question
The records of Norton, Inc. show the following for July: Standard labor-hours allowed per unit of output 1.3 Standard variable overhead rate per standard direct labor-hour $ 28 Good units produced 60,000 Actual direct labor-hours worked 80,000 Actual total direct labor $ 1,617,000 Direct labor efficiency variance $ 38,000 U Actual variable overhead $ 2,037,000
Required:
Compute the direct labor and variable overhead price and efficiency variances. (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.)
Direct labor:
Price variance:?
Efficiency variance:?
Variable overhead:
Price variance:?
Efficiency variance:?
Explanation / Answer
Direct labour efficiency variance = (Standard hour-actual hour)Standard rate
-38000 = (60000*1.3-80000)*X
-38000 = 78000X-80000X
-38000 = -2000X
X(standard rate) = 19 per hour
Direct labour efficiency varianc e= 19 per hour
Direct labour price variance = (19*80000-1617000) = 97000 U
Variabel overhead price variance = (28*80000-2037000) = 203000 F
Variable overhead efficiency variance = (60000*1.3-80000)*28 = 56000 U
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.