Shaylee Corp has $2.40 million to invest in new projects. The company's managers have presented a number of possible options that the board must prioritize. Information about the projects follows Project A Project B Project C Project D $ 670,000 S 350,000 $ 910,000 $ 1,065,000 Initial investment Present value of future cash flows 885,000 475,000 1,400,000 1,560,000 Required: 1. Is Shaylee able to invest in all of these projects simultaneously? Yes O No 2-a. Calculate the profitablity index for each project. (Round your answers to 4 decimal places.) Profitability Index Project A Project B Project C Project D 2-b. What is Shaylee's order of preference based on the profitability Index? Rank Project A Project B Project C Project DExplanation / Answer
1.No
Since the insufficient fund arises,he cannot invest in all project simultaneously.
2.
Profitability Index
= Present Value of Future Cash Flows / Initial Investment Required
PI of A =$885000/$670000=1.33
PI of B =$475000/350000=1.36
PI of C=$1400000/910000=1.54
PI of D=$1560000/1065000=1.46
3. Order of preference
Rank 1- C
Rank 2- D
Rank 3- B
Rank 4- A
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.