19 - The following data are given for Bahia Company: Round your final answer to
ID: 2522694 • Letter: 1
Question
19 - The following data are given for Bahia Company:
Round your final answer to the nearest dollar.
The fixed factory overhead volume variance is
a.$69,773 unfavorable
b.$69,773 favorable
c.$31,104 unfavorable
d.$31,104 favorable
Budgeted production (at 100% of normal capacity) 1,023 units Actual production 960 units Materials: Standard price per pound $1.82 Standard pounds per completed unit 12 Actual pounds purchased and used in production 11,174 Actual price paid for materials $22,907 Labor: Standard hourly labor rate $14.66 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,944 Actual total labor costs $75,396 Overhead: Actual and budgeted fixed overhead $1,133,000 Standard variable overhead rate $26.00 per standard labor hour Actual variable overhead costs $138,432 Overhead is applied on standard labor hours.Explanation / Answer
Fixed factory overhead volume variance = Absorbed Fixed overheads - Budgeted Fixed Overheads
= Actual Output x FOAR* - Budgeted Output x FOAR*
* Fixed Overhead Absorption Rate per unit of output
Now, FOAR = Budgeted Fixed Overheads / Budgeted Hours
= 11,33,000 / (1,023 x 4.3)
= 257.56 per hour
Therefore,
Fixed factory overhead volume variance = (960 x 4.3 x 257.56) - (1,023 x 4.3 x 257.56)
= -69,773 or 69,773 Unfavorable
Since actual production is less than the budgeted production, therefore fixed factory overhead volume variance will be unfavorable.
Hence, the correct answer is option a.$69,773 unfavorable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.