17 - Use this information for Harry Company to answer the question that follow.
ID: 2522673 • Letter: 1
Question
17 - Use this information for Harry Company to answer the question that follow. The following data are given for Harry Company:
Overhead is applied on standard labor hours. (Round interim calculations to the nearest cent.)
The direct labor rate variance is
a.$8,472.61 favorable
b.$20,936.97 unfavorable
c.$8,472.61 unfavorable
d.$20,936.97 favorable
Budgeted production 1,069 units Actual production 909 units Materials: Standard price per ounce $1.85 Standard ounces per completed unit 12 Actual ounces purchased and used in production 11,235 Actual price paid for materials $23,032 Labor: Standard hourly labor rate $14.44 per hour Standard hours allowed per completed unit 4.2 Actual labor hours worked 4,681 Actual total labor costs $76,066 Overhead: Actual and budgeted fixed overhead $1,032,000 Standard variable overhead rate $27.00 per standard labor hour Actual variable overhead costs $131,068Explanation / Answer
Option . C $ 8,472.61 unfavorable is correct answer
Direct labour rate variance
Actual labour hours worked( standard rate per hour - actual rate per hour)
Actual rate per hour = actual total labour ÷ Actual hours worked
So by putting value we can find actual rate per hour
$76066 ÷ 4681= 16.2499$ or rounded to nearest cent is $ $16.25
Actual hours worked= 4681
Standard labour rate per hour= $14.44
Actual labour rate per hour = $ 16.25
Labour rate variance
4681($14.44 -$16.25)= ($8472.61) or we can say
$8472.61 unfavorable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.