The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below:

The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 50 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune-ups:

Standard Hours Standard Rate Standard Cost Motor tune-up 2.5 $25.00 $62.50

Explanation / Answer

Labour efficiency variance = (Standard hour-actual hour)Standard rate

-350 = (50*2.5-X)25

-350 = 3125-25X

25X = 3475

X(actual hour) = 139 hour

Labour rate variance = (Standard rate-actual rate)actual hour

150 = (25*139-139X)

150 = 3475-139X

139X = 3325

X(Actual rate per hour) = 23.92 per hour