Lynyrd Skynyrd Company makes and sells a product called Product LS. Each unit of

ID: 2512617 • Letter: L

Question

Lynyrd Skynyrd Company makes and sells a product called Product LS. Each unit of Product LS requires 4.3 hours of direct labor at the rate of $22.00 per direct labor-hour. Management would like you to prepare a Direct Labor Budget for June.

The company plans to sell 26,000 units of Product LS in June. The finished goods inventories on June 1 and June 30 are budgeted to be 480 and 60 units, respectively. Budgeted direct labor costs for June would be: (Do not round intermediate calculations.)

rev: 11_19_2015_QC_CS-32026

$2,457,368

$2,419,868

$564,500

$2,438,618

Lynyrd Skynyrd Company makes and sells a product called Product LS. Each unit of Product LS requires 4.3 hours of direct labor at the rate of $22.00 per direct labor-hour. Management would like you to prepare a Direct Labor Budget for June.

The company plans to sell 26,000 units of Product LS in June. The finished goods inventories on June 1 and June 30 are budgeted to be 480 and 60 units, respectively. Budgeted direct labor costs for June would be: (Do not round intermediate calculations.)

Explanation / Answer

Calculate budgeted direct labour cost for june :

Production units in june = Sales units+Desired ending inventory-Beginning inventory

= 26000+60+-480

Production units in june = 25580 units

Budgeted direct labour cost for june = 25580*4.3*22 =2419868