Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. Assign overhead costs to the activity cost pools. 2. Calculate the activity r

ID: 2511805 • Letter: 1

Question

1. Assign overhead costs to the activity cost pools. 2. Calculate the activity rates for the activity cost pools. 3. Assign overhead costs to each product. Activity-based costing-Review Lake Corporation has an activity-based costing system with three activity costs pools Processing, Supervising, and Other. In the first stage allocations, costs in the two overhead accounts - equipment expense and indirect labor- are allocated to the three activity cost poolts based on resource consumption. Data used in the first stage allocations fllow Overhead costs: Equipment expense Indirect labor . $96,000 $4,000 . . Distribution of resource consumption across activity cost pools: Activity Cost Pools Processing 0.40 0.30 Other 0.40 0.20 Equipment expense 0.20 0.50 Indirect labor Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data for the company's two products follow Activity: Batches (Supervising) 400 600 1,000 MHs Product R4 Product L2 Total 6,800 13,200 20,000 Finally, the costs of Processing and Supervising are combined with the following sales and direct cost data to determine product margins Sales and direct cost data: Sales (total) Direct materials (total Direct labor (total) Product R4 $234,600 $81,100 $116,600 L2 $269,600 $120.200 $93,200 Required: 1. Assign overhead costs to the activity cost pools. (First-stage allocation). 2. Calculate the activity rates for the activity cost pools. 3. Assign overhead costs to each product. 4. Prepare a product margin report showing the product margin of each product

Explanation / Answer

Solution:

Part 1 – First Stage Allocation – Assignment of Overhead Costs to the activity cost pools

Processing

Supervising

Other

Total

Equipment expense

$38,400

$19,200

$38,400

$96,000

Indirect labor

$1,200

$2,000

$800

$4,000

Total

$39,600

$21,200

$39,200

$100,000

Part 2 – Activity Rates for the activity cost pools

Activity Cost Pool

Expected Manufacturing Overhead Costs (A)

Expected Activity Cost Driver (B)

Activity Rate (C = A/B)

Processing

$39,600

20000

Machine Hours

$1.98

per MH

Supervising

$21,200

1,000

Batches

$21.20

per batch

Other

$39,200

$100,000

Part 3 – Assign Overhead Costs to each product

Product R4

Product I.2

Activity Cost Pool

Activity Rate (C)

Activity Driver USAGE (H)

Overhead Assigned (C*H)

Activity Driver USAGE (E)

Overhead Assigned (C*E)

Processing

$1.98

per MH

6800

$13,464.00

13200

$26,136.00

Supervising

$21.20

per batch

400

$8,480.00

600

$12,720.00

Other

$0.00

$0.00

$21,944.00

$38,856.00

Part 4 – Product Margin Report

Product R4

Product I.2

Sales

$234,600

269600

Total Cost:

Direct materials

$81,100

$120,200

Direct Labor

$116,600

$93,200

Assigned Overhead Cost

$21,944

$38,856

Total Cost

$219,644

$252,256

Profit Margin (Sales - Total Cost)

$14,956

$17,344

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Processing

Supervising

Other

Total

Equipment expense

$38,400

$19,200

$38,400

$96,000

Indirect labor

$1,200

$2,000

$800

$4,000

Total

$39,600

$21,200

$39,200

$100,000