Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

a) Smith Industries uses activity-based costing to determine the costs of its tw

ID: 2508791 • Letter: A

Question

a) Smith Industries uses activity-based costing to determine the costs of its two products: A and B. The estimated total cost and expected number of activities for one of the company's activity cost pools are:

Cost

Product A

Product B

$14,000

400

300

Using activity-based costing, what is the activity rate for this activity?

b) Jones and Sons, Inc. uses activity-based costing to compute product costs. Estimated costs totaled $40,000 and expected number of activities equals 2,500 for a particular activity cost pool. The actual activity count for one of the products that Jones and Sons manufactures was 2,490. What is the amount of overhead applied for this product for this activity?

c) Bar-BQs-Are-Us has two products: A and B. The annual production level of Product A is 9,094 units. The annual production level of Product B is 15,826. The company uses activity-based costing and has prepared the following analysis showing the estimated total cost and expected number of activities for each of its three activity cost pools.

Overhead cost

Expected number of activities

Product A

Product B

Activity #1

$29,200

1000

500

Activity #2

$40,000

200

800

Activity #3

$180,000

600

5400

What is the activity rate for Activity #3?

d) For the products described in part c) find the overhead cost per unit for Product A.

Cost

Product A

Product B

$14,000

400

300

Explanation / Answer

A

total overhead cost

14000

total of expected number of activity

(400+300)

700

Activity rate per activity

total overhead cost/total of expected activity =14000/20

20

B-

expected activity rate

40000/2500

16

overhead applied to product

16*2490

39840

c-

activity rate for C

180000/(5400+6000)

30

D

Activity rate 1

(29200/1500)*1000

19466.67

Activity rate 2

(40000/1000)*200

8000

Activity rate -3

(180000/6000)*600

18000

total overhead allocated to A

45467

no of units of Product A produced

9094

Overhead rate per unit

45466.67/9094

5.000

A

total overhead cost

14000

total of expected number of activity

(400+300)

700

Activity rate per activity

total overhead cost/total of expected activity =14000/20

20

B-

expected activity rate

40000/2500

16

overhead applied to product

16*2490

39840

c-

activity rate for C

180000/(5400+6000)

30

D

Activity rate 1

(29200/1500)*1000

19466.67

Activity rate 2

(40000/1000)*200

8000

Activity rate -3

(180000/6000)*600

18000

total overhead allocated to A

45467

no of units of Product A produced

9094

Overhead rate per unit

45466.67/9094

5.000