Three different alternatives shown in table below are being considered by Kal Te
ID: 2507355 • Letter: T
Question
- Three different alternatives shown in table below are being considered by Kal Tech Engineering systems.
Assume that alternatives X and Z are replaced at the end of their lives.
Data Alternative X Alternative Y Alternative Z Initial Cost $6,000 $1,000 $1,500 Uniform Annual Benefits $810 $125 $ 230 Useful Life in Years 20 ? 10 MARR 12%
The most desirable alternative is ________. A. Alt. Y B. Alt. X C. Alt. Z D. Do nothing.
Assume that alternatives X and Z are replaced at the end of their lives.
Data Alternative X Alternative Y Alternative Z Initial Cost $6,000 $1,000 $1,500 Uniform Annual Benefits $810 $125 $ 230 Useful Life in Years 20 ? 10 MARR 12%
The most desirable alternative is ________. A. Alt. Y B. Alt. X C. Alt. Z D. Do nothing. Three different alternatives shown in table below are being considered by Kal Tech Engineering systems.
Assume that alternatives X and Z are replaced at the end of their lives.
Data Alternative X Alternative Y Alternative Z Initial Cost $6,000 $1,000 $1,500 Uniform Annual Benefits $810 $125 $ 230 Useful Life in Years 20 ? 10 MARR 12%
The most desirable alternative is ________.
The most desirable alternative is ________. Alt. Y Alt. X Alt. Z Do nothing. Data Alternative X Alternative Y Alternative Z Initial Cost $6,000 $1,000 $1,500 Uniform Annual Benefits $810 $125 $ 230 Useful Life in Years 20 ? 10
Explanation / Answer
B. Alt. X
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.