For two projects with the same cost, the one that is more risky has the: A. lowe

ID: 2507094 • Letter: F

Question

For two projects with the same cost, the one that is more risky has the: A. lowest standard deviation. B. lowest expected profit. C. highest standard deviation. D. highest expected profit. For two projects with the same cost, the one that is more risky has the: For two projects with the same cost, the one that is more risky has the: lowest standard deviation. lowest expected profit. highest standard deviation. highest expected profit. A. lowest standard deviation. B. lowest expected profit. C. highest standard deviation. D. highest expected profit.

Explanation / Answer

highest standard deviation. C. highest standard deviation.