Lampost Manufacturing provides the following information: To produce a unit of p
ID: 2502537 • Letter: L
Question
Lampost Manufacturing provides the following information:
To produce a unit of product:
Mixing department 4 minutes per unit
Molding department 7 minutes per unit
Casting department 9 minutes per unit
Finishing department 5 minutes per unit
There is a wait time of 5 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 8 minutes.
Required:
How long does it take to produce a batch of 20 units under a traditional manufacturing approach? (be sure to show all work)
Explanation / Answer
Let the manufacturing process start at t= 0
the time taken for this product for mfg = 4 + 5 + 7 + 10 + 9 + 8 + 5 = 48 min
but at t = 5min second unit manufacture starts
thus second unit is manufactured at time t = 53 min
similarly 19th unit is manufactured at t= 48 * 18*5 = 138 min
Time taken for complete manufacture ( i .e total tym) = 138 + 5 = 143 min