The standard costs and variances for direct materials, direct labor, and factory overhead for the month of May are as follows:
Direct materials$98,000 Price variance $4,300 Quantity variance $3,000 Direct labor 175,000 Rate variance 2,700 Efficiency variance 6,200 Manufacturing overhead 265,000 Spending variance 3,900 Volume variance 5,000
Determine the actual costs incurred during the month of May for direct materials, direct labor, and manufacturing overhead.
1) direct materials
2)direct labor
3)manufacturing overhead
Explanation / Answer
1. Standard Direct Material = 98000,
Price Variance = $4300,
Price Variance = (Actual Cost - Standrad Cost)
$4300 = (Actual Cost - $98000),
Actual Cost of Material = $98000 - $4300 = $93700
2. Standard Direct labour = $175000