The Fairmont Machine Shop wants to develop a cost estimating equation for its mo

ID: 2498948 • Letter: T

Question

The Fairmont Machine Shop wants to develop a cost estimating equation for its monthly cost of electricity. It has the following data:

Month

Cost of Electricity (Y)

Direct Labor-Hours (X)

January

$14,000

1,500

April

$15,000

1,700

July

$17,000

2,000

October

$14,500

1,600

What would be the best equation using the high-low method?

Y = $4,000 + $7X

Y = $0 + $9X

Y = $1,000 + $8X

Y = $5,000 + $6X

Month

Cost of Electricity (Y)

Direct Labor-Hours (X)

January

$14,000

1,500

April

$15,000

1,700

July

$17,000

2,000

October

$14,500

1,600

Explanation / Answer

We have,
at highest activity: x2 = 2,000; y2 = $17,000
at lowest activity: x1 = 1,500; y1 = $14,000

Variable Cost per Unit = ($17,000 $14,000) ÷ (2,000 1,500) = $6 per unit
Total Fixed Cost = $17,000 ($6 × 2,000) = $14,000 ($6 × 1,500) = $5,000
Cost Volume Formula: y = $5,000 + $6x