MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a contin
ID: 2496912 • Letter: M
Question
MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months:
Month
Management would like to know the company's throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:
Month
Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production in month 6 the move time, process time, and so forth, are the same as for month 5, except that the company is able to completely eliminate the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)
Month
1 2 3 4 Throughput time ? ? ? ? Manufacturing cycle efficiency ? ? ? ? Delivery cycle time ? ? ? ? Percentage of on-time deliveries 77% 78% 83% 90% Total sales (units) 10,430 10,540 10,540 10,560Management would like to know the company's throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:
Month
1 2 3 4 Move time per unit, in days 0.8 0.4 0.3 0.8 Process time per unit, in days 0.6 0.6 0.6 0.7 Wait time per order before startof production, in days 9.3 8.0 5.0 4.0 Queue time per unit, in days 3.0 3.0 2.0 1.0 Inspection time per unit, in days 0.6 0.6 0.4 0.7
Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production in month 6 the move time, process time, and so forth, are the same as for month 5, except that the company is able to completely eliminate the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)
Explanation / Answer
MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a contin
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.