The High Altitude Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 40-ski batch sizes. The finishing time is 5 minutes per ski. The assembly time is 9 minutes per ski. It takes 13 minutes to move a batch of skis from finishing to assembly.
a. Compute the value-added, non-value-added, and total lead time of this process.
Value-added lead time: __ minutes
Non-value-added lead time: __minutes
Total lead time: __minutes
b. Compute the value-added ratio. Round to one decimal place.
___%
Explanation / Answer
Answer :
Value added lead time = 14 min = (5 +9 ) minutes
Non Value added lead time :
Total within batch wait time = 546 = (5+9)min * ( 40- 1)
Move Time = 13
Total Lead time = 559
Value- added ratio = 14/ 559 = 2.5%