The High Altitude Ski Company manufactures skis in the finishing and assembly pr

ID: 2492523 • Letter: T

Question

The High Altitude Ski Company manufactures skis in the finishing and assembly process. Skis are manufactured in 40-ski batch sizes. The finishing time is 5 minutes per ski. The assembly time is 9 minutes per ski. It takes 13 minutes to move a batch of skis from finishing to assembly.

a. Compute the value-added, non-value-added, and total lead time of this process.

Value-added lead time: __ minutes

Non-value-added lead time: __minutes

Total lead time: __minutes

b. Compute the value-added ratio. Round to one decimal place.

___%

Explanation / Answer

Answer :

Value added lead time = 14 min = (5 +9 ) minutes

Non Value added lead time :

Total within batch wait time = 546    =      (5+9)min * ( 40- 1)

Move Time = 13

Total Lead time = 559

Value- added ratio = 14/ 559 = 2.5%