The manufacturing overhead budget at Cardera Corporation is based on budgeted direct labor-hours. The direct labor budget indicates that 7,300 direct labor-hours will be required in January. The variable overhead rate is $8.60 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $107,310 per month, which includes depreciation of $18,070. All other fixed manufacturing overhead costs represent current cash flows. The company recomputes its predetermined overhead rate every month. The predetermined overhead rate for January should be:
Explanation / Answer
Cardera Corporation Details Amt $ Budgeted fixed manufacturing OH for Jan 107,310 Budgeted Direct Labor Hours Jan 7,300 Fixed overhead rate per direct labor hour -Jan= 14.70 Variable Overhead rate per Direct Labor Hour Jan = 8.60 Total Predetermined Overhead Rate per Direct Labor Hour Jan =Fixed rate+Variable Rate per Direct Labor Hour= $ 23.30 per DLH
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.