On January 1, 2015, the City of Hastings created a solid waste landfill that it
ID: 2488203 • Letter: O
Question
On January 1, 2015, the City of Hastings created a solid waste landfill that it expects to reach capacity gradually over the next 20 years. If the landfill were to be closed at the current time, closure costs would be approximately $1.85 million plus an additional $790,000 for postclosure work. Of these totals, the city must pay $58,900 on December 31 of each year for preliminary closure work. At the end of 2015, the landfill reached 6 percent of capacity. At the end of 2016, the landfill reached 16 percent of capacity. Also at the end of 2016, a reassessment is made; total closure costs are determined to be $2.05 million rather than $1.85 million.
Assuming that the landfill is reported within the general fund, what journal entries are made in 2015 and 2016 on fund financial statements? (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
1. Record first payment of costs necessitated by eventual closure of landfill.
2. Record second payment of costs necessitated by eventual closure of landfill.
Explanation / Answer
1. Total estimated cost = $1,850,000+$790,000= $2,640,000
% of work completed = 6%
First payment cost = ($2,640,000*6%)+$58,900=$217,300
Landfil a/c dr 217,300
To cash a/c 217,300
2. Total estimated cost = $2,050,000+$790,000= $2,840,000
% of work completed = 16%
Second payment cost = [($2,840,000*16%)-($2,640,000*6%)]+$58,900=$354,900
Landfil a/c dr 354,900
To cash a/c 354,900
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.