Franklin Glass Works uses a standard cost system in which manufacturing overhead
ID: 2488004 • Letter: F
Question
Franklin Glass Works uses a standard cost system in which manufacturing overhead is applied on the basis of standard direct labor-hours. Each unit requires one standard hours of direct labor for completion. The denominator activity for the year was based on budgeted production of 130,000 units. Total overhead was budgeted at $1,000,000 for the year, and the fixed manufacturing overhead rate was $2.30 per direct labor-hour. The actual data pertaining to the manufacturing overhead for the year are presented below: Actual production 128,000 units Actual direct labor-hours 310,000 direct labor-hours Actual variable manufacturing overhead $222,000 Actual fixed manufacturing overhead $562,000 Franklin's fixed manufacturing overhead volume variance for the year is: $37,500 unfavorable $11,580 favorable $4,600 unfavorable $32,500 favorable
Explanation / Answer
Budgeted fixed overhead = Budgeted No. of labor hours x fixed overhead per hour
=130,000 x 2.30
= 299,000
Fixed overhead volume variance = (Budgeted fixed overhead x Units produced/ Budgeted production) - Budgeted fixed overhead
= (299,000 x 128,000 /130,000) - 299,000
= 294,400 -299,000
=4,600 Unfavorable