Percentage-of-completion and completed-contract methods. On March 15, 2016, Ambr
ID: 2487317 • Letter: P
Question
Percentage-of-completion and completed-contract methods. On March 15, 2016, Ambrose Contractors agreed to construct a building at a contract price of $18,000,000. Ambrose's estimated total construction costs are $12,000,000 and the project would be finished in 2018. Information relating to the costs and billings for this contract is as follows: Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and tor completed-contract accounting, show the gross profit that should be recorded for 2.10, 2.01, and 2018Explanation / Answer
2016 2017 2018 Total costs incurred to date $ 3,000,000 $ 9,450,000 $ 12,300,000 estimated costs to complete $ 9,000,000 $ 3,150,000 $ - % complete 25.00% 75.00% 100.00% Gross Profit to date $ 1,500,000 $ 4,050,000 $ 5,700,000 Gross Profit $ 1,500,000 $ 2,550,000 $ 1,650,000 Under completed contract reenue and gross profit are deferred untill project completed completed contract 2016 $ - 2017 $ - 2018 $ 5,700,000 % complete = Total construction costs to date/Total estimated costs of contract Gross profit to date = % complete X Total estimated gross profit Current year's gross profit = Gross profit to date - Gross profit in prior years
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.