Timothy Company has the following information available for October when 3,000 u
ID: 2485578 • Letter: T
Question
Timothy Company has the following information available for October when 3,000 units are produced:
Standard materials cost per unit
3.0 pounds at $4.10 per pound
Actual data for October:
Materials purchased
12,300 pounds at $4.20 per pound.
Materials used
11,750 pounds
The materials price variance is:
Timothy Company has the following information available for October when 3,000 units are produced:
Standard materials cost per unit
3.0 pounds at $4.10 per pound
Actual data for October:
Materials purchased
12,300 pounds at $4.20 per pound.
Materials used
11,750 pounds
The materials price variance is:
Explanation / Answer
materials price variance = ( standard rate - actual rate) * actual quantity
materials price variance = (4.10 - 4.20) * 11750 = - 1175
its negative value so its unfavourable