Suppose that a project has the following costs and bene ts over the rst three ye
ID: 2485113 • Letter: S
Question
Suppose that a project has the following costs and bene ts over the rst three years of its lifespan:
Year Benefits Costs
0 170 0
1 90 150
2 56 200
a) If the interest rate is 20% per year, what is the net present value of the project? What is the bene t-cost
ratio? Is the project worth it"?
b) How are your answers different if the interest rate is 10%? 30%?
Explanation / Answer
Year PV Factor @20% Benefit Cost PV of Benefits PV of Costs Year 0 1.000 170 - 170.00 - Year 1 0.833 90 150 75.00 125 Year 2 0.694 56 200 38.89 139 Total 283.89 263.89 a NPV of project = 20.00 Benefit /cost Ratio= 1.08 As the NPV is positive and benefit cost ratio> 1, the project is acceptable. b when interest is 10% Year PV Factor @10% Benefit Cost PV of Benefits PV of Costs Year 0 1.000 170 - 170.00 - Year 1 0.909 90 150 81.82 136 Year 2 0.826 56 200 46.28 165 Total 298.10 301.65 NPV of project = (3.55) Benefit /cost Ratio= 0.99 As the NPV is negative and benefit cost ratio 1, the project is acceptable.Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.