Allocating Selling and Administrative Expenses using Activity-Based Costing West
ID: 2484048 • Letter: A
Question
Allocating Selling and Administrative Expenses using Activity-Based Costing
Western Mechanical Inc. manufactures cooling units for commercial buildings. The price and cost of goods sold for each unit are as follows:
In addition, the company incurs selling and administrative expenses of $306,420. The company wishes to assign these costs to its three major customers, Coastal Atlantic University, Celebrity Arena, and Hope Hospital. These expenses are related to three major nonmanufacturing activities: customer service, project bidding, and engineering support. The engineering support is in the form of engineering changes that are placed by the customer to change the design of a product. The budgeted activity costs and activity bases associated with these activities are:
Activity-base usage and unit volume information for the three customers is as follows:
Required:
Hint(s)
1. Determine the activity rates for each of the three nonmanufacturing activity pools. Round to the nearest whole dollar.
2. Determine the activity costs allocated to the three customers, using the activity rates in (1).
3. Construct customer profitability reports for the three customers, dated for the year ended December 31, 2014, using the activity costs in (2). The reports should disclose the gross profit and income from operations associated with each customer. Enter all amounts as positive numbers, except for a negative income from operations.
Western Mechanical Inc.
Customer Profitability Report
For the Year Ended December 31, 2014
Coastal Atlantic University
Celebrity Arena
Hope Hospital
Revenues
$
$
$
Less cost of goods sold
Gross profit
$
$
$
Less selling and administrative activities:
Customer service
$
$
$
Project bidding
Engineering support
$
$
$
Income (loss) from operations
$
$
$
Price $680 per unit Cost of goods sold 410 Gross profit $270 per unitExplanation / Answer
1. In Activity Based costing the cost per unit is detemined by the acitivity is associated to. Therefore the calculation is as below:
2. The number of services/bids/engineering changes for each customer multiplied by the cost per unit respectively for these gives the total cost assciated with each customer as below:
3. Profitability statement is as below. Calcualtions has been explained in the same.
Activity Activity Rate Calculation Customer Service 141 per serv. req. Total Customer cost / No of service requests 33840/240 Project bidding 27 per bid Total Project bidding cost / No of bids 22680/840 Engineering Support 1470 per customer design change Total engineering cost/no of customer design changes 249900/170Related Questions