A company has identified the following overhead costs and cost drivers for the c
ID: 2483952 • Letter: A
Question
A company has identified the following overhead costs and cost drivers for the coming year:
Budgeted direct labor cost was $125,600 and budgeted direct material cost was $347,680. The following information was collected on three jobs that were completed during the year:
If the company uses activity-based costing (ABC), what is the cost of each unit of Job 102? (Round your final answer to 2 decimal places.)
Answer choices:
$281.60.
$464.60.
$329.80.
$376.60.
Budgeted Overhead Item Cost Driver Budgeted Cost Activity Level Machine setup Number of setups $ 23,100 210 Inspection Number of inspections 118,300 4,550 Material handling Number of material moves 91,500 6,100 Engineering Engineering hours 18,300 610Explanation / Answer
Activiy rates
Machine setup = $ 23,100 / 210 = $110, per setup
Inspection = $118,300 / 4,550 = $26 , per Inspection
Material handling = $91,500 / 6,100 = $15 per Material moves
Engineering = $18,300 / 610 = $30 per hours
Computation of Activity cost of Job 102
Cost per unit of Job 102 = $14,080 / 50 (number of units completed) = $281.60
Job 102 Amount Direct materials $9,750 Direct labor $2,200 Prime Cost $11,950 Add Overheads setups Cost ( 2 * $110) $220 Inspections (10 * $26) $260 Material moves (10* $15) $150 Engineering (50 * $30) $1,500 Total Cost $14,080Related Questions