The management of Zigby Manufacturing prepared the following estimated balance sheet for March, 2015:

The management of Zigby Manufacturing prepared the following estimated balance sheet for March, 2015:

ZIGBY MANUFACTURING Estimated Balance Sheet March 31, 2015 Assets Cash Accounts receivable Raw materials inventory Finished goods inventory $ 69,000 432,000 86,000 348,480 Total current assets Equipment, gross Accumulated depreciation 935,480 614,000 (157,000) Equipment, net 457,000 Total assets $ 1,392,480 Liabilities and Equity Accounts payable Short-term notes payable 178,700 19,000 $ 197,700 515,000 Total current liabilities Long-term note payable Total liabilities Common stock Retained earnings 712,700 342,000 337,780 Total stockholders' equity 679,780 Total liabilities and equity $ 1,392,480

Explanation / Answer

Solution:

1) Sales Budget

ZIGBY MANUFACTURING

Sales Budget

April, May and June 2015

Budgeted Unit Sales

Budgeted Unit Price

Budgeted Total Dollars

April 2015

18,000

$30

$540,000

May 2015

17,000

$30

$510,000

June 2015

20,700

$30

$621,000

55,700

$1,671,000

2) Production Budget

ZIGBY MANUFACTURING

Production Budget

April, May and June 2015

April

May

June

Next Month's Budgeted Sales (Units)

17,000

20,700

18,000

Ratio of Inventory to future sales

80%

80%

80%

Ending Inventory

13600

16560

14400

Budgeted Sales Units

18,000

17,000

20,700

Required Units of Available Production

31,600

33,560

35,100

Less: Beginning Inventory

-14,400

-13600

-16560

Units to be produced

17,200

19,960

18,540

3) Raw Material Budget

ZIGBY MANUFACTURING

Raw Materials Budget

April, May and June 2015

April

May

June

Production Budget (units)

17,200

19,960

18,540

Required Raw Material per finished unit (units)

0.5

0.5

0.5

Materials needed for production (units)

8600

9980

9270

Add: Ending Raw Material Inventory

4990

4635

4,700

Total Materials requirements (units)

13590

14615

13970

Less: beginning raw material inventory

-4,300

-4990

-4635

Materials to be purchased

9,290

9,625

9,335

Material Price per unit

$20

$20

$20

Total cost of direct material purchases

$185,800

$192,500

$186,700

4) Direct Labor Budget

ZIGBY MANUFACTURING

Raw Materials Budget

April, May and June 2015

April

May

June

Total

Production Budget (units)

17,200

19,960

18,540

55,700

Per Unit Labor Hours needed (hours)

0.5

0.5

0.5

0.5

Total Labor Hours Needed

8600

9980

9270

27850

Labor Rate per Hour

$22

$22

$22

$22

Labor dollars

$189,200

$219,560

$203,940

$612,700

Please ask separate question for rest part..

ZIGBY MANUFACTURING

Sales Budget

April, May and June 2015

Budgeted Unit Sales

Budgeted Unit Price

Budgeted Total Dollars

April 2015

18,000

$30

$540,000

May 2015

17,000

$30

$510,000

June 2015

20,700

$30

$621,000

55,700