Use the following data to find the direct labor cost variance. Direct labor standard (4 hrs. @ $5/hr.) $20 per unit Actual hours worked per unit 3.5 hours Actual units produced 3,800 units Actual rate per hour $5.50Use the following data to find the direct labor cost variance. Direct labor standard (4 hrs. @ $5/hr.) $20 per unit Actual hours worked per unit 3.5 hours Actual units produced 3,800 units Actual rate per hour $5.50
Use the following data to find the direct labor cost variance. Direct labor standard (4 hrs. @ $5/hr.) $20 per unit Actual hours worked per unit 3.5 hours Actual units produced 3,800 units Actual rate per hour $5.50
Use the following data to find the direct labor cost variance.
Explanation / Answer
Direct Labour Rate Variance = (Actual Rate - Standard Rate ) * Actual Hours worked
= ( 5.5 - 5) * 3800*3.5
= 6650 Unfavourable
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.