The following data is given for the Harry Company: Budgeted production 1,092 uni
ID: 2479976 • Letter: T
Question
The following data is given for the Harry Company:
Budgeted production 1,092 units
Actual production 971 units
Materials:
Standard price per ounce $1.8
Standard ounces per completed unit 10
Actual ounces purchased and used in production 9,419
Actual cost of materials $19,309
Labor:
Standard hourly labor rate $15.00 per hour
Standard hours allowed per completed unit 4.0
Actual labor hours worked 5,001
Actual total labor costs $76,265
Overhead:
Actual and budgeted fixed overhead $1,056,249
Standard variable overhead rate $26.00 per standard labor hour
Actual variable overhead costs $140,028
Overhead is applied on standard labor hours.
Determine the direct labor rate variance.
Select the correct answer.
$16,755 F
$1,250 U
$16,755 U
$18,005 U
Explanation / Answer
$5001 × (($76265/5001) – $15.0)
$5001 × (($15.24995) – $15.0)
= $5001 × $0.15
=1250 Unfavorable
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.