Venetian Company has two production departments, Fabricating and Assembling. At
ID: 2479411 • Letter: V
Question
Venetian Company has two production departments, Fabricating and Assembling. At a department managers meeting, the controller uses flexible budget graphs to explain total budgeted costs. Separate graphs based on direct labor hours are used for each department. The graphs show the following. 1. At zero direct labor hours, the total budgeted cost line and the fixed cost line intersect the vertical axis at $ 53,000 in the Fabricating Department and $ 43,000 in the Assembling Department. 2. At normal capacity of 46,100 direct labor hours, the line drawn from the total budgeted cost line intersects the vertical axis at $ 131,370 in the Fabricating Department, and $ 93,710 in the Assembling Department. Compute the total budgeted cost for each department, assuming actual direct labor hours worked were 49,100 and 43,100, in the Fabricating and Assembling Departments, respectively.Explanation / Answer
Part 1
Therefore Fixed cost in Fabricating Department is = $53000
And Variable cost per direct labour hours = $0
2. At zero direct labour hours, Total Budgeted cost in Assembling Department is = $43000
Therefore Fixed cost in Assembling department is = $43000
And Variable cost per direct labour hours = $0
Fabricating Department
Total Budgeted cost =$ 131370
Fixed Cost = $53000
Variable Cost / hour= (131370-53000)/46100
= $1.7/hour
Therefore
Total Budgeted Cost Formula = Fixed Cost + (Direct labour Hour* Variable Cost /hour)
= $ 53000 + $ (46100*1.7)
=$ 53000 + $ 78370
= $131370
Assembling Department
Total Budgeted cost =$ 93710
Fixed Cost = $43000
Variable Cost / hour= (93710-43000)/46100
= $1.1/hour
Therefore
Total Budgeted Cost Formula = Fixed Cost + ( Direct labour Hour* Variable Cost /hour)
= $ 43000 + $ (46100*1.1)
=$ 43000 + $ 50710
= $93710
Part 2
a) When direct labour hours = 49100 hours
Fabricating Department
Fixed Cost =$ 53000
Variable Cost =$ 1.7/hour
(As always calculated at normal capacity)
Total Budgeted Cost Formula = Fixed Cost + (Direct labour Hour* Variable Cost /hour)
= $ 53000 + $ (49100*1.7)
=$ 53000 + $ 83470
= $136470
Assembling Department
Fixed Cost =$ 53000
Variable Cost =$ 1.7/hour
(As always calculated at normal capacity)
Total Budgeted Cost Formula = Fixed Cost + (Direct labour Hour* Variable Cost /hour)
= $ 43000 + $ (49100*1.1)
=$ 43000 + $ 54010
= $97010
b) When direct labour hours = 43100 hours
Fabricating Department
Fixed Cost =$ 53000
Variable Cost =$ 1.7/hour
(As always calculated at normal capacity)
Total Budgeted Cost Formula = Fixed Cost + (Direct labour Hour* Variable Cost /hour)
= $ 53000 + $ (43100*1.7)
=$ 53000 + $ 73270
= $126270
Assembling Department
Fixed Cost =$ 53000
Variable Cost =$ 1.7/hour
(As always calculated at normal capacity)
Total Budgeted Cost Formula = Fixed Cost + (Direct labour Hour* Variable Cost /hour)
= $ 43000 + $ (43100*1.1)
=$ 43000 + $ 47410
= $90410
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.