Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Limerock Custom Builders was established in 1971 by Jon Rock and initially built

ID: 2476586 • Letter: L

Question

Limerock Custom Builders was established in 1971 by Jon Rock and initially built high-quality customized homes under contract with specific buyers. In the 1990s. Rock's son joined the company and expanded Limerock's activities into industri.il and commercial retail markets. Upon the retirement of Limerock's long-time financial manager. Risk s son recently hired Flint, a former college friend, as the new controller for Limerock. Flint, has been associated with a public accounting firm for the last 6 years. Upon reviewing Limerock's accounting practices. Flint observed that Limerock followed the completed-contract method of rrvenue recognition, a carryover front the years when individual home building was the majority of Linterock's operations. Several years ago. the predominant portion of Limrock's activities shifted to the commerical retail and industrial building areas. From land acquisions to the completion of construction, most building contracts cover several years. Under the circumstances. Flint believes that Limeorck should follow the percentage-of-completion method of accounting. From a typical building contract, Flint developed the following data. Explain the difference between completed-contract revenue recognition and percentage-of-completion revenue recognition. Using tin- data provided for the Sunshine Mall and assuming the percentage-of-completion method of revenue recognition is used, calculate Limerock's revenue and gross profit for 2014. 201?, and 2016. under each of the following circumstances. Assume that all costs an- incurred, all billings to customers are made, and all collections from customers are received within 30 days of billing, as planned. Further assume that, as a result of unforeseen local ordinances and the fact that the building site was in a wetlands area, Limerock experienced cost overruns of 5800.000 in 2014 to bring the site into compliance with the ordinances and to overcome wetlands barriers to construction further assume that, in addition to the cost overruns of $800,000 for this contract incurred under part (b)(2), inflationary factors over and above those anticipated in the development of the original contract cost have mused an additional cost overrun of $900, 000 in 201? It is not anticipated that any cost overruns will occur in 2016.

Explanation / Answer

The logic behind the percentage-of-completion method is that both the buyer and seller have obtained enforceable rights. The buyer has the right to require specific performance on the contract; the seller has the right to require progress payments. Thus the facts seem to indicate that a continuous “sale” is in progress.

According to Statement of Position 81-1, the percentage method should be used if estimates of progress toward completion, revenues, and costs are reasonably dependable, and all the following conditions exist:

If these conditions have not been met, then the completed-contract method should be used. It should be emphasized that the total profit on the construction project is the same under both methods.

The difference between methods is simply a question of timing—the percentage method recognizes profit little by little over time, while the completed-contract method defers the entire profit until completion.

Contract Price = $12,000,000

Percentage of work completed = Expenditure incurred from Inception to date / Total Estimated costs.

Revenue Recognized = Percentage of work completed * Total contract value

(b)(1)

2014

2015

2016

Estimated Costs

           3,000,000

           4,200,000

           2,800,000

Cumulative estimated costs

           3,000,000

           7,200,000

         10,000,000

Total estimated costs

         10,000,000

         10,000,000

         10,000,000

Percentage of work completed

0.3 or 30%

0.72 or 72%

1 or 100%

Contract Value

         12,000,000

         12,000,000

         12,000,000

Cumulative Estimated Revenue

           3,600,000

           8,640,000

         12,000,000

Estimated revenue for that year

           3,600,000

           5,040,000

           3,360,000

Estimated Costs

          3,000,000

           4,200,000

           2,800,000

Gross profit

               600,000

               840,000

               560,000

(b)(2)

2014

2015

2016

Estimated Costs

           3,800,000

           4,200,000

           2,800,000

Cumulative estimated costs

           3,800,000

           8,000,000

         10,800,000

Total estimated costs

         10,800,000

         10,800,000

         10,800,000

Percentage of work completed

                      0.35

                      0.74

                      1.00

Contract Value

         12,000,000

         12,000,000

         12,000,000

Cumulative Estimated Revenue

           4,200,000

           8,880,000

         12,000,000

Estimated revenue for that year

           4,200,000

           4,680,000

           3,120,000

Estimated Costs

          3,800,000

           4,200,000

           2,800,000

Gross profit

               400,000

               480,000

               320,000

(b)(3)

2014

2015

2016

Estimated Costs

           3,800,000

           5,100,000

           2,800,000

Cumulative estimated costs

           3,800,000

           8,900,000

         11,700,000

Total estimated costs

         11,700,000

         11,700,000

         11,700,000

Percentage of work completed

                      0.32

                     0.76

                      1.00

Contract Value

         12,000,000

         12,000,000

         12,000,000

Cumulative Estimated Revenue

           3,840,000

           9,120,000

         12,000,000

Estimated revenue for that year

           3,840,000

           5,280,000

           2,880,000

Estimated Costs

           3,800,000

           5,100,000

           2,800,000

Gross profit

                 40,000

               180,000

                 80,000

2014

2015

2016

Estimated Costs

           3,000,000

           4,200,000

           2,800,000

Cumulative estimated costs

           3,000,000

           7,200,000

         10,000,000

Total estimated costs

         10,000,000

         10,000,000

         10,000,000

Percentage of work completed

0.3 or 30%

0.72 or 72%

1 or 100%

Contract Value

         12,000,000

         12,000,000

         12,000,000

Cumulative Estimated Revenue

           3,600,000

           8,640,000

         12,000,000

Estimated revenue for that year

           3,600,000

           5,040,000

           3,360,000

Estimated Costs

          3,000,000

           4,200,000

           2,800,000

Gross profit

               600,000

               840,000

               560,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote