Levine Inc., which produces a single product, has prepared the following standar
ID: 2475278 • Letter: L
Question
Levine Inc., which produces a single product, has prepared the following standard cost sheet for one unit of the product.Direct materials (6 pounds at $1.60 per pound) $9.60 Direct labor (3 hours at $11.00 per hour) $33.00
During the month of April, the company manufactures 180 units and incurs the following actual costs.
Direct materials purchased and used (2,400 pounds) $4,320 Direct labor (560 hours) $6,048
Compute the total, price, and quantity variances for materials and labor.
Total materials variance $
UnfavorableFavorableNeither favorable nor unfavorable
Materials price variance $Neither favorable nor unfavorableFavorableUnfavorable
Materials quantity variance $Neither favorable nor unfavorableUnfavorableFavorable
Total labor variance $FavorableUnfavorableNeither favorable nor unfavorable
Labor price variance $Neither favorable nor unfavorableFavorableUnfavorable
Labor quantity variance $UnfavorableNeither favorable nor unfavorableFavorable
Explanation / Answer
1.Total material variance=SP *SQ-AP*AQ
SP=Standard price
SQ=Standard quantity
AP=Actual price
AQ=Actual quantity
Actual material price per pound=Total material cost/Total material quantity=4320/2400=1.8 per pound
Actual price =1.8
Total material variance=1.6 *1080-1.8*2400=-2592 U
Standard quantity=Standard pounds used per unit * Quantity produced=6*180=1080 pounds
2. Material price variance=Actual quantity * Actual price-Actual quantity *Standard price
Material price variance=2400*1.8-2400*1.6=480 U
3. Material quantity variance=Actual quantity * Standard price –Standard quantity *Standard price
Material quantity variance=2400*1.6-1080*1.8=1896 U
4. Total labour variance=Standard rate * Standard hours-Actual rate * Actual hours
Standard hours=Standard hour required in one unit *Number of units =3*180=540 hours
Actual hours=560 hours
Standard rate=$11 per hour
Actual rate=Total labour cost/Actual number of hours=6048/560=10.8
Total labour variance=11*540-10.8*560=-108 U
5. Labour quantity variance=Standard hours * Standard rate –Actual hours *Standard rate
Labour quantity variance=540*11-560*11=-220 U
6. Labour price variance=Actual hours*Standard rate-Actual hours*Actual rate
Labour price variance=560*11-560*10.8=112 F
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.